Use of the EVM method for analysis of extending the construction project duration as a result of realization disturbances - case study
Wykorzystanie metody EVM do analizy wydłużenia czasu trwania inwestycji budowlanej w wyniku wystąpienia zakłóceń realizacji - studium przypadku
Autorzy:
Starczyk-Kołbyk, Anna
Kruszka, Leopold
Powiązania:
https://bibliotekanauki.pl/articles/1852345.pdf
Data publikacji:
2021
Wydawca:
Polska Akademia Nauk. Czytelnia Czasopism PAN
Tematy:
metoda EVM
zakłócenia
opóźnienie
roboty budowlane
EVM method
earned value management method
disturbance
delay
construction work
Opis:
In pursuing numerous construction projects, investors and contractors regularly face construction delay problems, many of which are likely to have been avoidable. There is found that payment delays and project delays are the two most critical effects of risk factors of construction management. The paper presents the practical application of the Earned Value Management method, which was used to estimate the possible extension of the duration of construction works during which realization disturbances occurred on the example of selected construction investment. The realization disturbances are usually an inseparable element in the implementation of construction works. They are the result of, among others: additional works, changes or design defects, as well as a badly adopted logistics strategy regarding the supply of construction materials. Delays or increasing the total cost of investment is a problem often encountered in the implementation of construction investments, despite advanced construction technologies, including system technologies and proven tools supporting the management of the construction process. The EVM method is used to control investments. It allows you to control delays and acceleration of construction works as well as to estimate their cost and completion date. In the analyzed case it was used to determine the scale of delays arising in construction works and related effects with the specification of the participation of individual participants of the investment process for delays. This paper is a continuation and supplementation of the research presented in the article: “The influence of construction works disturbances on the EVM analysis outcomes – case study” [23].
Realizując liczne projekty budowlane, inwestorzy i wykonawcy regularnie spotykają się z problemami dotyczącymi opóźnienia robót budowlanych, z których wielu prawdopodobnie można byłoby uniknąć. Stwierdzono, że opóźnienia w płatnościach i w realizacji inwestycji to dwa najbardziej krytyczne skutki czynników ryzyka związane z zarządzaniem budową. W artykule przedstawiono praktyczne zastosowanie metody Earned Value Management, która posłużyła do oszacowania możliwego wydłużenia czasu trwania robót budowlanych, podczas których wystąpiły zakłócenia budowlane na przykładzie wybranej inwestycji budowlanej. Nieodłącznym elementem realizacji robót budowlanych są zwykle zakłócenia budowlane. Są wynikiem m.in.: dodatkowych prac, zmian czy wad projektowych, a także źle przyjętej strategii logistycznej w zakresie dostaw materiałów budowlanych. Opóźnienia lub wzrost całkowitego kosztu inwestycji to problem często napotykany przy realizacji inwestycji budowlanych, pomimo zaawansowanych technologii budowlanych, w tym technologii systemowych i sprawdzonych narzędzi wspomagających zarządzanie procesem budowlanym. Do kontroli inwestycji stosowana jest metoda EVM. Pozwala kontrolować opóźnienia i przyspieszenie prac budowlanych oraz oszacować ich koszt i termin zakończenia. W analizowanym przypadku posłużył on do określenia skali opóźnień powstających w robotach budowlanych i związanych z nimi skutków. Niniejszy artykuł jest kontynuacją i uzupełnieniem badań przeprowadzonych na inwestycji budowlanej, przedstawionych w pracy: „Wpływ zakłóceń robót budowlanych na wyniki analizy EVM – studium przypadku” w 2020 r. [23].
Źródło:
Archives of Civil Engineering; 2021, 67, 3; 373-393
1230-2945
Pojawia się w:
Archives of Civil Engineering
Dostawca treści:
Biblioteka Nauki
Artykuł
Tytuł:
Use of the EVM method for analysis of extending the construction project duration as a result of realization disturbances - case study
Wykorzystanie metody EVM do analizy wydłużenia czasu trwania inwestycji budowlanej w wyniku wystąpienia zakłóceń realizacji - studium przypadku
Autorzy:
Starczyk-Kołbyk, Anna
Kruszka, Leopold
Powiązania:
https://bibliotekanauki.pl/articles/1852451.pdf
Data publikacji:
2021
Wydawca:
Polska Akademia Nauk. Czytelnia Czasopism PAN
Opis:
In pursuing numerous construction projects, investors and contractors regularly face construction delay problems, many of which are likely to have been avoidable. There is found that payment delays and project delays are the two most critical effects of risk factors of construction management. The paper presents the practical application of the Earned Value Management method, which was used to estimate the possible extension of the duration of construction works during which realization disturbances occurred on the example of selected construction investment. The realization disturbances are usually an inseparable element in the implementation of construction works. They are the result of, among others: additional works, changes or design defects, as well as a badly adopted logistics strategy regarding the supply of construction materials. Delays or increasing the total cost of investment is a problem often encountered in the implementation of construction investments, despite advanced construction technologies, including system technologies and proven tools supporting the management of the construction process. The EVM method is used to control investments. It allows you to control delays and acceleration of construction works as well as to estimate their cost and completion date. In the analyzed case it was used to determine the scale of delays arising in construction works and related effects with the specification of the participation of individual participants of the investment process for delays. This paper is a continuation and supplementation of the research presented in the article: “The influence of construction works disturbances on the EVM analysis outcomes – case study” [23].
Realizując liczne projekty budowlane, inwestorzy i wykonawcy regularnie spotykają się z problemami dotyczącymi opóźnienia robót budowlanych, z których wielu prawdopodobnie można byłoby uniknąć. Stwierdzono, że opóźnienia w płatnościach i w realizacji inwestycji to dwa najbardziej krytyczne skutki czynników ryzyka związane z zarządzaniem budową. W artykule przedstawiono praktyczne zastosowanie metody Earned Value Management, która posłużyła do oszacowania możliwego wydłużenia czasu trwania robót budowlanych, podczas których wystąpiły zakłócenia budowlane na przykładzie wybranej inwestycji budowlanej. Nieodłącznym elementem realizacji robót budowlanych są zwykle zakłócenia budowlane. Są wynikiem m.in.: dodatkowych prac, zmian czy wad projektowych, a także źle przyjętej strategii logistycznej w zakresie dostaw materiałów budowlanych. Opóźnienia lub wzrost całkowitego kosztu inwestycji to problem często napotykany przy realizacji inwestycji budowlanych, pomimo zaawansowanych technologii budowlanych, w tym technologii systemowych i sprawdzonych narzędzi wspomagających zarządzanie procesem budowlanym. Do kontroli inwestycji stosowana jest metoda EVM. Pozwala kontrolować opóźnienia i przyspieszenie prac budowlanych oraz oszacować ich koszt i termin zakończenia. W analizowanym przypadku posłużył on do określenia skali opóźnień powstających w robotach budowlanych i związanych z nimi skutków. Niniejszy artykuł jest kontynuacją i uzupełnieniem badań przeprowadzonych na inwestycji budowlanej, przedstawionych w pracy: „Wpływ zakłóceń robót budowlanych na wyniki analizy EVM – studium przypadku” w 2020 r. [23].
Źródło:
Archives of Civil Engineering; 2021, 67, 3; 373-393
1230-2945
Pojawia się w:
Archives of Civil Engineering
Dostawca treści:
Biblioteka Nauki
Artykuł
Tytuł:
The influence of construction works disturbances on the EVM analysis outcomes - case study
Wpływ zakłóceń robót budowlanych na wyniki analizy EVM - studium przypadku
Autorzy:
Starczyk-Kołbyk, Anna
Kruszka, Leopold
Powiązania:
https://bibliotekanauki.pl/articles/230183.pdf
Data publikacji:
2020
Wydawca:
Polska Akademia Nauk. Czytelnia Czasopism PAN
Tematy:
zakłócenie budowlane
opóźnienie
roboty budowlane
zmiana planu
kara umowna
metoda wartości wypracowanej
building disturbance
delay
construction works
schedule change
contractual penalty
earned value management method
Opis:
The paper presents the problem of building disturbances, which are usually an inseparable element during the implementation of construction projects. They were classified, their causes and sides of the construction process responsible for their creation were identified on the basis of the analyzed construction investment. In addition, using the Earned Value Management method, the scale of delays arising in construction works and the related effects were determined. The important role of close cooperation and good communication between all participants of the construction process was emphasized, which would reduce the phenomenon of building disturbances, but also mitigate the negative effects of delays that have already occurred.
W artykule dokonano szczegółowej analizy procesu inwestycyjnego na etapie wykonawstwa wybranej współczesnej inwestycji kubaturowej finansowanej ze środków budżetowych. Przedstawiono również problem zakłóceń budowlanych, które są z reguły nieodłacznym elementem podczas realizacji przedsięwzięć budowlanych oraz dokonano ich klasyfikacji. Po przeprowadzeniu szczegółowej analizy przedmiotowego procesu budowlanego zidentyfikowano występujące zakłócenia budowlane na badanej inwestycji obejmujące łącznie 1165 dni realizowanego okresu wykonawstwa.
Źródło:
Archives of Civil Engineering; 2020, 66, 1; 161-177
1230-2945
Pojawia się w:
Archives of Civil Engineering
Dostawca treści:
Biblioteka Nauki
Artykuł

Ta witryna wykorzystuje pliki cookies do przechowywania informacji na Twoim komputerze. Pliki cookies stosujemy w celu świadczenia usług na najwyższym poziomie, w tym w sposób dostosowany do indywidualnych potrzeb. Korzystanie z witryny bez zmiany ustawień dotyczących cookies oznacza, że będą one zamieszczane w Twoim komputerze. W każdym momencie możesz dokonać zmiany ustawień dotyczących cookies