Cost analysis of a two-unit cold standby system subject to degradation, inspection and priority
Analiza kosztów dwu-elementowego systemu z rezerwą zimną z uwzględnieniem degradacji, kontroli stanu systemu oraz priorytetowości zadań
Autorzy:
Kumar, J.
Kadyan, M. S.
Malik, S. Ch.
Powiązania:
https://bibliotekanauki.pl/articles/301970.pdf
Data publikacji:
2012
Wydawca:
Polska Akademia Nauk. Polskie Naukowo-Techniczne Towarzystwo Eksploatacyjne PAN
Tematy:
degradacja
kontrola stanu
priorytetowość
analiza zysku
degradation
inspection
priority
profit analysis
Opis:
The present paper deals with a reliability model incorporating the idea of degradation, inspection and priority. The units may fail completely directly from normal mode. There is a single server who visits the system immediately when required. The original unit undergoes for repair upon failure while only replacement of the duplicate unit is made by similar new one. The original unit does not work as new after repair and so called degraded unit. The system is considered in up-state if any one of new/duplicate/degraded unit is operative. The server inspects the degraded unit at its failure to see the feasibility of repair. If repair of the degraded unit is not feasible, it is replaced by new one similar to the original unit in negligible time. The priority for operation to the new unit is given over the duplicate unit. The distribution of failure time follow negative exponential where as the distributions of inspection, repair and replacement times are assumed as arbitrary. The system is observed at suitable regenerative epochs by using regenerative point technique to evaluate mean time to system failure (MTSF), steady-state availability, busy period and expected number of visits by the server. A particular case is considered to see graphically the trend of mean time to system failure (MTSF), availability and profit with respect to different parameters.
Niniejsza praca dotyczy modelu niezawodności uwzględniającego zagadnienia degradacji, kontroli stanu oraz priorytetowości zadań. Elementy mogą ulegać całkowitemu uszkodzeniu bezpośrednio z trybu normalnego. Istnieje jeden konserwator, który odwiedza system, gdy tylko zachodzi taka potrzeba. W przypadku uszkodzenia, element oryginalny podlega naprawie, podczas gdy element zapasowy (duplikat) podlega jedynie wymianie na nowy, podobny. Po naprawie, element oryginalny nie działa już jako element nowy lecz jako element zdegradowany. System uważa się za zdatny jeżeli pracuje którykolwiek z trzech typów elementów: nowy/rezerwowy/zdegradowany. W przypadku uszkodzenia elementu zdegradowanego, konserwator przeprowadza kontrolę stanu elementu, aby stwierdzić możliwość realizacji naprawy. Jeżeli naprawa elementu zdegradowanego jest niemożliwa, zostaje on wymieniony, w czasie pomijalnym, na element nowy, podobny do elementu oryginalnego. Nowy element uzyskuje priorytet pracy w stosunku do elementu rezerwowego. Rozkład czasu uszkodzenia jest rozkładem wykładniczym ujemnym, a rozkłady czasów kontroli stanu, naprawy i wymiany przyjmuje się jako rozkłady dowolne. System obserwuje się w odpowiednich okresach odnowy wykorzystując technikę odnowy RPT (regenerative point technique) w celu ocenienia średniego czasu do uszkodzenia systemu (MTSF), gotowości stacjonarnej, okresu zajętości oraz oczekiwanej liczby wizyt konserwatora. Przebiegi MTSF, gotowości i zysków w funkcji różnych parametrów przedstawiono w formie graficznej na podstawie studium przypadku.
Źródło:
Eksploatacja i Niezawodność; 2012, 14, 4; 278-283
1507-2711
Pojawia się w:
Eksploatacja i Niezawodność
Dostawca treści:
Biblioteka Nauki
Artykuł
Tytuł:
Reliability and Profit Analysis of a Single-Unit System with Preventive Maintenance Subject to Maximum Operation Time
Analiza niezawodności i zysku dla systemu jednoelementowego z konserwacją zapobiegawczą poddanego maksymalnemu czasowi pracy
Autorzy:
Kadyan, M. S.
Powiązania:
https://bibliotekanauki.pl/articles/302041.pdf
Data publikacji:
2013
Wydawca:
Polska Akademia Nauk. Polskie Naukowo-Techniczne Towarzystwo Eksploatacyjne PAN
Tematy:
system jednoelementowy
niezawodność
konserwacja zapobiegawcza
maksymalny czas pracy
analiza zysku
single-unit system
reliability
preventive maintenance
maximum operation time
profit analysis
Opis:
This paper deals with the profit analysis of a reliability model for a single-unit system in which unit fails completely either directly from normal mode or via partial failure. The partially failed operating unit is shutdown after a maximum operation time for preventive maintenance. There is a single server who attends the system immediately whenever needed to conduct preventive maintenance at partial failure stage and repair at completely failure stage of the unit. The unit works as new after preventive maintenance and repair. The switch devices are considered as perfect. All random variables are assumed as independent and uncorrelated. The distribution of failure times, maximum operation time, preventive maintenance time and repair time are taken as general. Various reliability characteristics of interest are evaluated by using semi-Markov process and regenerative point technique. The tabular represantation of mean time to system failure (MTSF), availability and profit with respect to maximum rate of operation time has also been shown for a particular case.
W niniejszej pracy przedstawiono analizę zysku modelu niezawodności dla systemu jednoelementowego, w którym element ulega całkowitemu uszkodzeniu bezpośrednio z trybu normalnego lub pośrednio na skutek częściowego uszkodzenia. Częściowo uszkodzona działająca jednostka jest wyłączana po upłynięciu maksymalnego czasu pracy w celu przeprowadzenia konserwacji zapobiegawczej. Pojedynczy serwer wspomaga bezzwłocznie system w momencie wystąpienia potrzeby przeprowadzenia konserwacji zapobiegawczej na etapie częściowego uszkodzenia oraz naprawy na etapie uszkodzenia całkowitego. Element działa jak nowy, po konserwacji zapobiegawczej i naprawie. Stan przełączników sieciowych uznaje się za doskonały. Wszystkie zmienne losowe traktowano jako niezależne i nieskorelowane. Rozkład czasów uszkodzeń, maksymalnego czasu pracy, czasu konserwacji zapobiegawczej i czasu naprawy przyjęto jako ogólne. Wybrane parametry niezawodnościowe oceniano za pomocą procesu semimarkowskiego i techniki odnowy RPT. Dla poszczególnych przykładów przedstawiono także tabelaryczne zestawienie średniego czasu do uszkodzenia systemu (MTSF), gotowości i zysku w odniesieniu do maksymalnego czasu pracy.
Źródło:
Eksploatacja i Niezawodność; 2013, 15, 2; 176-181
1507-2711
Pojawia się w:
Eksploatacja i Niezawodność
Dostawca treści:
Biblioteka Nauki
Artykuł
Tytuł:
An integrated model of production scheduling and maintenance planning under imperfect preventive maintenance
Model zintegrowany harmonogramowania produkcji i planowania obsługi technicznej w ramach niepełnej konserwacji zapobiegawczej
Autorzy:
Chen, X.
Xiao, L.
Zhang, X.
Xiao, W.
Li, J.
Powiązania:
https://bibliotekanauki.pl/articles/301817.pdf
Data publikacji:
2015
Wydawca:
Polska Akademia Nauk. Polskie Naukowo-Techniczne Towarzystwo Eksploatacyjne PAN
Tematy:
aperiodic imperfect preventive maintenance
production scheduling
maintenance planning
immune clonal selection algorithm
total profit
nieokresowa niepełna konserwacja zapobiegawcza
harmonogramowanie produkcji
planowanie konserwacji
algorytm odpornościowej selekcji klonalnej
całkowity zysk
Opis:
For a successful company, machines are always required to work continuously to make more profit in a certain period. However, machines can be unavailable due to the scheduled maintenance activities or unexpected failures. Hence, a model connected production scheduling with maintenance planning for a production line which is composed of multiple machines is developed. Suppose preventive maintenance is imperfect and cannot renew all the machines. Age reduction factor and hazard rate increase factor are introduced to illustrate the imperfect character. Aperiodic preventive maintenance policy is adopted. Replacement as perfect maintenance could restore the machine “as good as new”. When and whether to perform replacement is based on a cost-time rate function which is defined to judge whether or not the preventive maintenance is economical. The objective of the joint model is to maximize the total profit which is composed of production value, production cost, maintenance cost (including the preventive maintenance cost and replacement cost), and tardiness cost (which is related to the job sequence and maintenance activities). To optimize the objective, immune clonal selection algorithm is utilized. The proposed model is validated by a numerical example.
Aby firma mogła działać z powodzeniem i przynosić większe zyski w danym okresie czasu, zainstalowane w niej maszyny muszą pracować w sposób nieprzerwany. Niestety, z powodu planowych działań obsługowych lub nieoczekiwanych awarii, maszyny są czasami wyłączane z produkcji. Dlatego też w niniejszym artykule opracowano model łączący harmonogramowanie produkcji z planowaniem obsługi technicznej dla linii produkcyjnej złożonej z wielu maszyn. W pracy założono, że konserwacja zapobiegawcza jest niepełna i nie prowadzi do odnowy wszystkich maszyn. Aby zilustrować jej niepełny charakter, wprowadzono pojęcia czynnika redukcji wieku oraz czynnika wzrostu wskaźnika zagrożenia. Przyjęto politykę nieokresowej konserwacji zapobiegawczej. Wymiana jako forma pełnej konserwacji pozwala na przywrócenie maszyny do stanu "fabrycznej nowości". Kiedy i czy należy przeprowadzić wymianę zależy od funkcji wskaźnika kosztu w stosunku do czasu, który pozwala ocenić, czy konserwacja zapobiegawcza jest opłacalna. Model zintegrowany ma na celu maksymalizację całkowitego zysku, który jest wypadkową wartości produkcji, kosztów produkcji, kosztów obsługi (w tym kosztów konserwacji zapobiegawczej oraz kosztów wymiany) i kosztów nieterminowego zakończenia zadania (ang. lateness, związanych z kolejnością wykonywanych zadań i czynności obsługowych). Aby zoptymalizować opisany cel, wykorzystano algorytm odpornościowej selekcji klonalnej Proponowany model zweryfikowano na przykładzie liczbowym.
Źródło:
Eksploatacja i Niezawodność; 2015, 17, 1; 70-79
1507-2711
Pojawia się w:
Eksploatacja i Niezawodność
Dostawca treści:
Biblioteka Nauki
Artykuł
Tytuł:
Multi-state model of maintenance policy
Wielostanowy model decyzji eksploatacyjnych
Autorzy:
Knopik, L.
Migawa, K.
Powiązania:
https://bibliotekanauki.pl/articles/1365592.pdf
Data publikacji:
2018
Wydawca:
Polska Akademia Nauk. Polskie Naukowo-Techniczne Towarzystwo Eksploatacyjne PAN
Tematy:
maintenance
preventive replacement
profit per unit time
availability
lifetime distribution
failure rate function
IFR class
MTFR class
utrzymanie
wymiany prewencyjne
zysk na jednostkę czasu
gotowość
rozkład czasu życia
funkcja intensywności uszkodzeń
klasa IFR
klasa MTFR
Opis:
Preventive replacement is applied to improve the device availability or increase the profit per unit time of the maintenance system. In this paper, we study age-replacement model of technical object for n-state system model. The criteria function applied in this paper describe profit per unit time or coefficient of availability. The probability distribution of a unit‘s failure time is assumed to be known, and preventive replacement strategy will be used over very long period of time. We investigate the problem of maximization of profit per unit time and coefficient availability for increasing the failure rate function of the lifetime and for a wider class of lifetime. The purpose of this paper is to obtain conditions under which the profit per unit time approaches a maximum. In this paper we shows that the criteria function (profit per unit time or coefficient availability) can be expressed using the matrix calculation method. Finally, a numerical example to evaluate an optimal replacement age is presented.
Wymiany prewencyjne stosuje się w celu podnoszenia gotowości systemów eksploatacji maszyn i wzrostu dochodu na jednostkę czasu systemu eksploatacji. W pracy analizuje się model wymian obiektów technicznych według wieku dla n-stanowego systemu. Funkcja kryterialna stosowana w pracy wyraża zysk przypadający na jednostkę czasu lub współczynnik gotowości. Zakłada się, że rozkład prawdopodobieństwa czasu do uszkodzenia obiektu technicznego jest znany i strategia wymian prewencyjnych będzie stosowana na długim przedziale czasowym. Bada się problem maksymalizacji zysku na jednostkę czasu i współczynnika gotowości dla rosnącej funkcji intensywności uszkodzeń lub funkcji intensywności z szerszej klasy. Celem tej pracy jest sformułowanie warunków, przy których zysk na jednostkę czasu osiąga maksimum. W pracy pokazano, że badaną funkcję kryterialną (zysk na jednostkę czasu lub współczynnik gotowości) można wyrazić za pomocą metod rachunku macierzowego. Na końcu pracy przedstawiono przykład numeryczny oceny optymalnego wieku wymiany dla rzeczywistego procesu eksploatacji.
Źródło:
Eksploatacja i Niezawodność; 2018, 20, 1; 125-130
1507-2711
Pojawia się w:
Eksploatacja i Niezawodność
Dostawca treści:
Biblioteka Nauki
Artykuł
Tytuł:
Semi-Markov system model for minimal repair maintenance
Semi-markowski model systemu obsługi z minimalną naprawą
Autorzy:
Knopik, Leszek
Migawa, Klaudiusz
Powiązania:
https://bibliotekanauki.pl/articles/1365296.pdf
Data publikacji:
2019
Wydawca:
Polska Akademia Nauk. Polskie Naukowo-Techniczne Towarzystwo Eksploatacyjne PAN
Tematy:
age-replacement
minimal repair
perfect repair
profit per time unit
availability
semi-Markov processes
preventive maintenance
corrective maintenance
wymiana według wieku
naprawa minimalna
naprawa dokładna
zysk na jednostkę czasu
gotowość
procesy semi-Markowa
obsługa prewencyjna
obsługa korekcyjna
Opis:
This paper analyzes the semi-Markov model of technical objects age-replacements. The model includes two types of repairs: perfect repairs and minimal repairs. Minimal repairs in semi-Markov models have been studied in literature only to an extent. In this paper, the asymptotic availability coefficient and profit per time unit are considered as criteria for the quality of the system operation. The paper formulates various conditions for the occurrence of the maximum of criteria functions. The two numerical examples given at the end of the paper illustrate the results obtained in the paper.
W pracy bada się semimarkowski model wymian według wieku obiektów technicznych. W modelu uwzględnia się dwa rodzaje napraw: naprawy dokładne i naprawy minimalne. Naprawy minimalne w modelach semimarkowskich były badane w literaturze w niewielkim stopniu. Jako kryteria jakości pracy systemu rozważa się asymptotyczny współczynnik gotowości i zysk przypadający na jednostkę czasu. W pracy sformułowano różne warunki istnienia maksimum funkcji kryterialnych. Podane na końcu pracy dwa przykłady numeryczne ilustrują wyniki uzyskane w pracy.
Źródło:
Eksploatacja i Niezawodność; 2019, 21, 2; 256-260
1507-2711
Pojawia się w:
Eksploatacja i Niezawodność
Dostawca treści:
Biblioteka Nauki
Artykuł
    Wyświetlanie 1-5 z 5

    Ta witryna wykorzystuje pliki cookies do przechowywania informacji na Twoim komputerze. Pliki cookies stosujemy w celu świadczenia usług na najwyższym poziomie, w tym w sposób dostosowany do indywidualnych potrzeb. Korzystanie z witryny bez zmiany ustawień dotyczących cookies oznacza, że będą one zamieszczane w Twoim komputerze. W każdym momencie możesz dokonać zmiany ustawień dotyczących cookies