Tytuł:
Application of the work breakdown structure in determining cost buffers in construction schedules
Autorzy:
Połoński, M.
Powiązania:
https://bibliotekanauki.pl/articles/231132.pdf
Data publikacji:
2015
Wydawca:
Polska Akademia Nauk. Czytelnia Czasopism PAN
Tematy:
szacowanie kosztów
niepewność
koszt nieprzewidziany
bufor kosztu
struktura podziału pracy
projekt budowlany
cost estimating
uncertainty
contingent cost
cost buffer
work breakdown structure
construction project
Opis:
The paper presents methods of determining the location of cost buffers and corresponding contingency costs in the CPM schedule based on its work breakdown structure. Application of correctly located cost buffers with appropriately established reserve costs is justified by the common overrunning of scheduled costs in construction projects. Interpolated cost buffers (CB) as separate tasks have been combined with relevant summary tasks by the starttostart (SS) relationship, whereas the time of their execution has been dynamically connected with the time of accomplishment of particular summary tasks using the “paste connection” option. Besides cost buffers linked with the group of tasks assigned to summary tasks, a definition of the cost buffer for the entire project (PCB) has been proposed, i.e. as one initial task of the entire project. Contingency costs corresponding to these buffers, depending on the data that the planner has at his disposal, can be determined using different methods, but always depend on the costs of all tasks protected by each buffer. The paper presents an exemplary schedule for a facility and the method of determining locations and cost for buffers CB and PCB, as well as their influence on the course of the curve illustrating the budgeted cost of work scheduled (BCWS). The proposed solution has been adjusted and presented with consideration of the possibilities created by the scheduling software MS Project, though its general assumptions may be implemented with application of other similar specialist tools.
Źródło:
Archives of Civil Engineering; 2015, 61, 1; 147-161
1230-2945
Pojawia się w:
Archives of Civil Engineering
Dostawca treści:
Biblioteka Nauki
Artykuł
    Wyświetlanie 1-1 z 1

    Ta witryna wykorzystuje pliki cookies do przechowywania informacji na Twoim komputerze. Pliki cookies stosujemy w celu świadczenia usług na najwyższym poziomie, w tym w sposób dostosowany do indywidualnych potrzeb. Korzystanie z witryny bez zmiany ustawień dotyczących cookies oznacza, że będą one zamieszczane w Twoim komputerze. W każdym momencie możesz dokonać zmiany ustawień dotyczących cookies