Problemy konstrukcyjno-konserwatorskie w kompleksie "Emir Kurkumas" w Kairze The constructional and conservation problems of the ameer qurqumas COMPLEX, CAIRO
Although the state of preservation of the Ameer Qurqumas
complex, Cairo can justly be described as one
relatively satisfactory it is beyond any doubt that it
requires a good deal of constructional work aimed at
strengthening of structure of the preserved monument
that at the same time will enable its adaptation to
the new functions. The above complex was already
subjected to some preservating treatments in 1916—>18
and in 1941—43 which, however, did not bring as
a consequence any total strengthening of its structure
as their scope was confined to fairly negligible superficial
repairs.
The works carried out at present by a group of Polish
experts were purposed to cover the following two
stages: (a) a detailed reconnaissance and examination
of destructions and technical assessment of structural
qualities of materials applied for its erection as well
as that of usability of the preserved elements, (b) preparing
of general scheme of the whole project and
designing for both conservation and constructional
works.
In the course of preliminary works enabling to underhas
been carried out of causes of destruction and also
carefully calculated the stresses present in the most
loaded piers and walls as well as the values characterizdng
the strength of original materials.
In view of differences apparent in structural patterns
in the separate portions of the comdlex each of them
has been individually considered as a structural entity
with the appropriate allowances made for
a broad margin of security. To be most endangered
proved the piers in mausoleum for which a need has
arisen to make a set of detailed statical calculations.
It followed from the above calculations that
the “opus emplectum” system adopted in the building
is being loaded nearly up to the extreme limit of its
theoretical strength wheraas the foundations are in
perfect condition and do not need any strengthening
at all.
The strength of limestone used for construction has,
as a resut of tests, been determined as that amounting
to a value of 120 kG/cm2 whereas that of mortar as
that of 8 kG/cm2. The above tests have been carried
out by the use of two methods that is that macroscopic
and in a laboratory. In addition to the above
tests has been examined the stability of walls and in
particular the cracks were tested by placing of control
cement “cakes” with glass strips inserted between
them; finally, the preserved structural elements made
of timber were also subjected to examination.
A number of constructional measures has been provided
within the general scheme. As the most complicated
among them are to be named those connected with
strengthening of piers in mausoleum where the cracked
stone blocks are to be replaced with new ones
meetings the extremely severe requirements of description
and those of execution techniques. In some
places where the existing walls erected from limestone
blocks have completely lost their cohesion it has
proved indispensable to provide for anastilosis. In
places where the basic mass of walls has decayed
and poured the thus formed cavities and cracks will
be filled with a thin cement mortar injected by
pressure.
The design provides also for technical requirements
of execution of the building’s new portions where
those original have totally decayed, as it is the case,
for instance, with walls, floors or vaultings.
As the traces of the original structural patterns, corresponding
with that required by the future functions
■and structural strength have been preserved almost in
all portions of the buiding the new elements will in
principle resemble those original as to their basic
forms and materials.
In addition to the detailed outlines to the design have
been included the requirements that are to be complied
to by the newly applied building materials and so,
for example, the stone material should be of the same
kind as that used originally, the mortars should have
the strength of 15 kG/cm2 and for their preparing
should be used the quartz sand.
A permanent supervision over the building work performed
by an engineer-conservator has been planned
which the provision is in full accordance with general
practice adopted in Egypt. The works conducted in the
Ameer Qurqumas complex will allow to gain some
new experiences in conservation of the monuments of
Islamic art and to utilize them both in Poland and
in other objects im Egypt.
Ta witryna wykorzystuje pliki cookies do przechowywania informacji na Twoim komputerze. Pliki cookies stosujemy w celu świadczenia usług na najwyższym poziomie, w tym w sposób dostosowany do indywidualnych potrzeb. Korzystanie z witryny bez zmiany ustawień dotyczących cookies oznacza, że będą one zamieszczane w Twoim komputerze. W każdym momencie możesz dokonać zmiany ustawień dotyczących cookies
Informacja
SZANOWNI CZYTELNICY!
UPRZEJMIE INFORMUJEMY, ŻE BIBLIOTEKA FUNKCJONUJE W NASTĘPUJĄCYCH GODZINACH:
Wypożyczalnia i Czytelnia Główna: poniedziałek – piątek od 9.00 do 19.00