The paper presents the concept of repowering in existing power plant. Among technologies
for existing steam power plants, the hot windbox repowering is the fastest way to respond to
the energy demand, improve efficiency and reduce the pollutants emissions. Thermodynamic
analysis of power plant model with fossil boiler before and after hot windbox repowering, has
been investigated using commercial software. The purpose of this work is to understand and
analyze the effect of hot windbox repowering on 387 MW fossil fuel power plant as well as the
effect of additional heat exchangers, which have been installed parallel with regeneration system
to use the heat of boiler exhaust gases. In this way, after repowering the summary power of
power plant in base load is 615 MW, which has been reached adding gas turbine (176.9 MW).
To analyze the model, calculations were performed in 3 stages: 1) calculation and comparison of
the thermodynamic parameters as well as carbon dioxide emissions of power plant model before
and after repowering, 2) analysis of the optimal value of feed water mass flow through heat
exchangers installed after economizer, 3) calculation of thermodynamic parameters in values
100%, 90%, 80% and 75% of fossil boiler heat loads.
Ta witryna wykorzystuje pliki cookies do przechowywania informacji na Twoim komputerze. Pliki cookies stosujemy w celu świadczenia usług na najwyższym poziomie, w tym w sposób dostosowany do indywidualnych potrzeb. Korzystanie z witryny bez zmiany ustawień dotyczących cookies oznacza, że będą one zamieszczane w Twoim komputerze. W każdym momencie możesz dokonać zmiany ustawień dotyczących cookies
Informacja
SZANOWNI CZYTELNICY!
UPRZEJMIE INFORMUJEMY, ŻE BIBLIOTEKA FUNKCJONUJE W NASTĘPUJĄCYCH GODZINACH:
Wypożyczalnia i Czytelnia Główna: poniedziałek – piątek od 9.00 do 19.00